Hammer Bldg.: Airflow Testing and Balancing on Floors 3, 4, and 7 Beginning May 31

We will be conducting airflow testing and balancing on floors 3, 4, and 7 of Hammer Health Sciences Center according to the following schedule:

Baseline Airflow Measurements: This work will have a very minimal impact on floor occupants.

  • Wednesday, May 31: Floors 4 and 7
  • Monday, June 5: Floors 3 and 4

Onsite Rebalancing: This work will require some access to interstitial spaces and ceilings, which can create some noise in adjacent spaces. Our vendor will identify impacted spaces and work with occupants in advance of any ceiling-related work to minimize any disturbances.

  • Monday, June 12 through Friday, June 16: Floors 4 and 7
  • Monday, June 19 through Friday, June 23: Floors 3 and 4

If you have any questions or concerns about this upcoming work, please contact Anton Dedukaj, west campus building manager, at agd2143@cumc.columbia.edu or 646-830-6219.