Department of Pharmacology Expansion
We renovated and converted an amphitheater, offices, corridors, and restrooms on several floors of the Vagelos College of Physicians and Surgeons Building into a new, state-of-the-art wet laboratory research facility for the Department of Pharmacology under the leadership of Dr. Corinne T. Abate-Shen.
Amphitheater 5/7 Renovation Project Fact Sheet
Project Location: Vagelos College of Physicians and Surgeons Building, Amphitheater 5/7
Client: Department of Pharmacology
Project Program: Renovated laboratories and administrative support spaces
Project Scope: Gut renovation/conversion of a multi-floor amphitheater; major infrastructure replacement
Project Area: 6,644 GSF
Architect: HLW
MEP Engineer: AKF Group
Commissioning Agent:
Contractor: Structure Tone
Project Manager: Fernando Bedoya
Project Status: Completed
7th Floor Renovations Project Fact Sheet
Project Location: Vagelos College of Physicians and Surgeons Building, 7th floor
Client: Department of Pharmacology
Project Program: Office conversion to wet research laboratory space
Project Scope: Gut renovation/conversion of existing office space; major infrastructure replacement
Project Area: 3,174 GSF
Architect: Mitchell Giurgola Architects, LLP
MEP Engineer: AKF Group
Commissioning Agent: Enica Engineers
Contractor: Structure Tone
Project Manager: Fernando Bedoya
Project Status: Completed
Construction Progress Updates
Activities listed are subject to change based on approval, University events, other requirements, and unforeseen circumstances. While the renovations are being completed, there will be intermittent periods of increased noise, vibration, and dust.
For questions or concerns related to this project, please contact Fernando Bedoya, senior project manager, at fb2330@cumc.columbia.edu.
March 2023
- Construction is complete.
- Final furniture installations and occupant relocations will take place over several weeks.
February 2023
- Substantial construction activity is anticipated to be finished in VP&S Amphitheater 5/7 later this month.
- Once completed, new furniture will be installed.
January 2023
Construction activity continues to take place in VP&S Amphitheater 5/7.
- Ongoing work includes the construction of new ceilings, painting, and installation of new flooring and new casework.
- The installation of new supplemental A/C units for the specialized equipment rooms continues this month.
- Renovation efforts also continue in the men's, women’s, and single-stall restrooms located on the 7th floor.
- We also are replacing the hallway ceilings and exterior windows in the hallways adjacent to the project areas on the 5th and 7th floors.
December 2022
Construction activity continues to take place in VP&S Amphitheater 5/7.
- Ongoing work included the construction of new ceilings, painting, and installation of new flooring and new casework.
- We also began to replace the hallway ceilings and exterior windows in the hallways adjacent to the project areas on the 5th and 7th floors.
November 2022
- Ongoing work included the construction of new partitions, electrical roughing, plumbing, and mechanical piping installation, and ductwork installation.
- Renovation efforts also continued in the men's, women’s, and single-stall restrooms located on the 7th floor.
October 2022
- Ongoing work included the construction of new partitions, electrical roughing, plumbing, mechanical piping installation, and ductwork installation.
- Renovation efforts also began in the men's and women’s restrooms located on the 7th floor.
- Additionally, construction began on a new single-stall, ADA restroom on the 7th floor.
September 2022
- Installation of new steel framing, decking, and concrete pour for new floor has been completed.